Turnaround and reduced CO2 emissions at OCI Melamine plant, Chemelot, the Netherlands
On average, one of our production plants is shut down for major maintenance (Turnaround) every four years. This month, it's the turn of one of our melamine plants. The plant will be shut down, maintenance work carried out, inspections conducted, cleaning operations performed and a number of major improvement projects implemented. According to Plant Manager Rob Jan Venhuizen: "The most important project is the installation of a new energy-efficient 'stripper', which will ensure that we reduce energy consumption and CO2 emissions."
Senior Turnaround Manager Frank Hovestadt continues: "Approximately 450 pipes, vessels, machines, valves and spring safety devices will be inspected during this shutdown. In addition, we also have 550 stop points for maintenance and improvement projects." So we have three weeks within which to process more than 1,000 stop points. This involves a total of 60,000 hours of work, which requires 500 people and calls for a great deal of preparation. "Work planners have looked at what the work involves in detail. They will assess any risks and put appropriate measures in place. In everything we do, safety comes first. We need to improve our safety performance, which is why we are working hard on our 'One in Safety' campaign.
Turnarounds are very busy times and require teamwork and team spirit. "Once the plant is in top shape again and running at maximum capacity, we'll be proud of a job well done," says Rob-Jan Venhuizen
Latest news
New Biostoom waste-to-energy plant delivers steam and electricity to Borealis in Beringen, Belgium
New state-of-the-art power station transforms non-recyclable waste from local households into electricity and steam. Successful first deliveries of steam and electricity to Borealis Beringen operat...
Yara ready to enable the hydrogen economy with historic full-scale green ammonia project in Porsgrunn, Norway
Yara announces plans for 500,000 tonnes per annum green ammonia production in Norway, powering emission-free shipping fuels and decarbonized food solutions. Yara plans to broaden its core, by enabl...
Construction of Clariant's sunliquid® plant in Podari, Romania on track for completion by the end of 2021
Construction continues with over 650 workers on site operating in full compliance with all COVID-19 pandemic precaution measurements. Majority of large key production equipment has already been ins...
New production facility for aromatic ring chlorination in Frankfurt-Höchst, Germany
WeylChem Group of Companies (WCGC), announced the larger scale investment in a new production facility for aromatic ring chlorination to be built at the Group’s site in Frankfurt-Höchst