Neste refinery is getting ready for the major turnaround in Porvoo, Finland
Neste Corporation - Neste secures the safe and undisrupted operations of the Porvoo refinery in Finland with major turnarounds, executed approximately every five years. The Porvoo refinery major turnaround was originally planned for the spring 2020, but due to the coronavirus pandemic, the turnaround execution in planned scope was not possible and only the most critical maintenance works were completed in spring 2020.
After thorough planning work, the Porvoo refinery is preparing to execute a major turnaround starting in April. The duration of the turnaround is approximately 12 weeks. The shutdown of the process units will begin in stages on Monday 5 April 2021. After the maintenance work, the refinery is expected to be operating normally by the end of June.
In the major turnaround, the refinery is subject to regulatory inspections, maintenance works and selected asset improvement initiatives that are required for the refinery's operations. The total investments of the Porvoo refinery major turnaround are estimated to be around EUR 330 million.
“Major turnaround is a significant investment to secure safety, availability and competitiveness of the Porvoo refinery for the next operating cycle. During the turnaround, we will execute several investment projects related to the development of the refinery, including extensive asset, automation and electrification renewals,” says Marko Pekkola, Executive Vice President, Oil Products.
In order to manage the pandemic situation during the turnaround, a detailed health security plan has been prepared. It defines the planned extensive measure to mitigate the impacts of the coronavirus. The measures include, for example, mandatory usage of face masks, keeping a safe distance and enhanced hand hygiene at the site, a negative test result prior to entering the site and regular testing during the turnaround, as well as effective monitoring of compliance throughout the turnaround.
“We at Neste are committed to arranging a safe working environment during the Porvoo major turnaround. In all turnaround related works, we ensure the health and wellbeing of our employees, suppliers and partners, especially during the exceptional corona pandemic situation. We work closely and in good cooperation with various authorities and follow the Finnish state and regional guidelines and requirements strictly,” explains Hannele Jakosuo-Jansson, Senior Vice President, HR, HSSEQ and Procurement.
The turnaround will not affect the product deliveries to Neste’s customers. The Neste harbour and distribution terminal in Porvoo are operating normally during the major turnaround.
Countries
Companies
Latest news
PureCycle’s First Plastic Recycling Plant in Europe located in Antwerp-Brugges NextGen District, Belgium
The new plant is expected to have an annual capacity of 59,000 metric tons, with opportunities to expand operations with an anticipated total capacity of approximately 240,000 metric tons per year.
CABB site in Kokkola, Finland: vital growth with a focus on sustainability
CABB Group will invest more than EUR 50 million by 2025 in expanding its facilities at its site in Kokkola, Finland. A new office building is also being constructed. Special attention is being pai...
TotalEnergies commissions BioBéarn, the country’s largest anaerobic digestion unit in Mourenx, France
The project will convert 220,000 metric tons of organic waste into 200,000 metric tons per year of digestate, a natural fertilizer, and 160 GWh of biomethane. This new unit allowing to avoid the em...
Borealis, committed to lead the transformation to a circular economy, acquires a majority stake in Renasci’s Ostend facility, Belgium
Borealis increases its financial investment in Renasci to acquire a majority shareholding position of 50.01%. Investment will provide Borealis increasing access to chemically recycled feedstock, st...