Stora Enso’s pilot plant for a breakthrough bioplastic is well underway at the Langerbrugge recycled paper mill near Ghent
The launch of a new bioplastics pilot plant in the Flanders region in Belgium will enable a new bioplastics production technology, ready for implementation at industrial scale.
In the decades to come, bio-based materials will be standard components of various packaging solutions. As a response to this demand, In December 2019, Stora Enso announced an investment of EUR 9 million to build a pilot facility enabling the production of bioplastics. The objective is to test FuraCore®, Stora Enso’s breakthrough technology to produce furandicarboxylic acid (FDCA), a major building block of bioplastic PEF (PolyEthylene Furanoate).
From pilot production in 2022 towards commercialisation in 2026
Since the initial investment announcement, things have advanced at a rapid pace. Construction of the plant has been completed, and the commissioning is well underway. Initial production will start by year-end 2022, and, after that, things will quickly move towards regular production of FDCA, and PEF with partners.
According to VP Emerging Business, Dirk den Ouden, the next step is to ensure everything runs in a stable way and to collect data for the next scale-up. Once samples are available in large enough quantities, Stora Enso will work with partners and potential customers on validating the FuraCore® products in a range of applications.
– We’ll soon have our pilot fully up and running, producing material for testing, says den Ouden. The proof point of years of breakthrough R&D is now around the corner.
The bigger picture of the piloting effort is to validate the chemical process and provide sample material to gain further insight into market needs and product demands. The pilot facility will initially use industrially available sugar (fructose) to produce high-value chemicals and materials for application testing. In the future, the intention is to run the process on sugars extracted from wood and other non-food-based biomass.
- Nature happens to provide our raw material in a very efficient way via crops. That’s where we’ll start. Implementing FuraCore® chemistry at large scale globally, however, requires us to rethink our raw material sourcing. That’s where sugars from trees and agricultural residues come in.
The Flanders region as a hub for bio-based technologies
With the Flanders region having become a focal point for the bio-based economy, it would be an ideal region to industrialize the FuraCore® process. The central location of the pilot facility at the Langerbrugge recycled paper mill near Ghent brings access to skilled people and critical service providers in the region. At just an hour from Brussels, it makes partner visits easy to arrange.
The journey of developing a plastic that makes sense is in full swing.
– Come and join us, Den Ouden concludes, and be part of a renewable packaging revolution.
Categories
Chemical substances
Countries
Companies
Latest news
Solvay to produce green hydrogen for its Peroxides activity in Rosignano, Italy
Partnership with Sapio will develop Europe's first hub for the production of green hydrogen peroxide by mid-2026 and help decarbonize the plant.
Carbios and Indorama Ventures reaffirm partnership to build first-of-a-kind PET biorecycling plant in Longlaville, France
Under the agreement Carbios should acquire 13ha land from Indorama Ventures’ existing PET plant at Longlaville and expects to be granted permits by Q3 2023, allowing start of construction by end of...
Plug power makes major strategic move into Finland’s green hydrogen economy with its proven PEM Electrolyzer and Liquefaction technology at Kokkola, Kristinestad and Porvoo
Plug plans to develop three green hydrogen production plants in Finland for European markets, working with multiple financial and industrial partners
ACC inaugurates its first Gigafactory in Billy-Berclau/Douvrin, France
This Gigafactory includes over 60,000 m2 of workshops, with an initial production line with a capacity of more than 13 GWh, rising to 40 GWh by 2030. A local, skilled workforce that will contribute...