bp selects Johnson Matthey’s LCH™ technology for its first low carbon (blue) hydrogen project H2Teesside in The United Kingdom
- Johnson Matthey’s LCH™ technology selected for bp’s H2Teesside project, which at aims to be one of the UK’s largest low carbon (blue) hydrogen facilities.
- H2Teesside targets 1.2GW of hydrogen production by 2030 – over 10% of the UK Government’s hydrogen target of 10GW by 2030.
- The selection marks a significant milestone for bp’s H2Teesside project as it continues its development and commences its detailed design.
- The licence is the 8th sustainable technologies project contributing to JM’s milestone of winning more than ten additional large-scale projects across Catalyst Technologies and Hydrogen Technologies by end of 2023/24.
Johnson Matthey (JM), a global leader in sustainable technologies, and bp have signed a licensing and engineering agreement for Johnson Matthey’s LCH technology at bp’s proposed flagship low carbon (blue) hydrogen facility in Teesside, H2Teesside.
Industry in the Tees Valley accounts for 64% of total local CO₂ emissions, compared to 24% nationally [1]. H2Teesside would help power and decarbonise local industry here, as well as new businesses attracted to this low carbon hydrogen produced at scale.
Due to its proximity to domestically sourced North Sea natural gas, established pipe corridors, and planned carbon capture transportation and storage infrastructure that is being developed by the bp-led Northern Endurance Partnership, the area is uniquely placed for H2Teesside to help lead a low carbon transformation, supporting jobs, regeneration, and the revitalisation of the surrounding area.
H2Teesside will use JM’s innovative LCH technology, which couples a gas-heated reformer with an autothermal reformer (GHR-ATR). LCH offers the lowest natural gas usage commercially available today and can capture up to 99% of carbon dioxide produced. This means for H2Teesside it would deliver the lowest levelised cost of hydrogen (LCOH) and the most carbon efficient technology available today for low carbon (blue) hydrogen production.
H2Teesside, alongside NZT Power and BOC Teesside Hydrogen, was selected by the UK Government as Track-1 Capture Projects to proceed to negotiations for government funding from the Department for Energy Security & Net Zero (DESNZ), for the East Coast Cluster as part of Phase 2 of the cluster sequencing process for CCUS.
Alberto Giovanzana, Managing Director – CT Licensing at Johnson Matthey, said: “bp’s H2Teesside project will be at the forefront of the UK’s efforts to decarbonise, and we’re proud JM’s innovative LCH technology will be at the heart of it. We championed the use of low carbon (blue) hydrogen as a part of our efforts to achieve net zero emissions and have proven ourselves as a trusted partner with this licence representing our fifth major LCH project globally.”
Will Harrison-Cripps, H2Teesside Asset Development Lead at bp, said: “H2Teesside, which aims to be one of the first low carbon hydrogen production facilities in the UK, is a key part of our plans to help Teesside transform into the UK’s leading hydrogen hub, providing a diverse range of customers with low carbon hydrogen produced at scale. We are pleased to be working with Johnson Matthey, using their innovative technology to accelerate the pace of hydrogen deployment as we work towards commercial operations in 2028 and supporting the East Coast Cluster decarbonise a range of industries in Teesside.”
[1] Tees Valley Net Zero Cluster Plan Key Findings, Tees Valley Net Zero Project Board
Categories
Investments
2021-03-01
at Wilton International (UK)Countries
Companies
Latest news
Sandoz inaugurates new antibiotic production plant in Austria and new biosimilar development center in Germany
Investment of EUR 175 million reaffirms Sandoz commitment to long-term leadership in off-patent medicines New penicillin production process will significantly improve ecological footprint and help...
Air Products to Build Europe’s Largest Blue Hydrogen Plant and Strengthens Long-term Agreement in Rotterdam, The Netherlands
The facility is expected to be on-stream in 2026, and the resulting "blue" hydrogen product to serve ExxonMobil’s (Esso) Rotterdam refinery and additional customers via Air Products' hydrogen pipel...
OMV and Interzero establish joint venture to build and operate Europe’s largest sorting facility for chemical recycling in Walldürn, Germany
innovative, fully automatic, sorting plant with capacity of up to 260,000 tonnes per year. Mixed plastics into feedstock for OMV’s chemical recycling. Investment volume over EUR 170 mn
Carbios obtains building and operating permits, in line with announced schedule, for world’s first PET biorecycling plant in Longlaville, France
This authorization allows construction work to start as planned for the plant’s commissioning in 2025. The plant will have a capacity of 50,000 tons of PET waste and will create 150 jobs